RBP captain: Public safety will not be impacted in Rehoboth Friday, May 24, 2024
Opening of Rehoboth’s temp Boardwalk restrooms delayed Tuesday, May 21, 2024 Combi Wall
Rehoboth Beach Patrol project facing delays Friday, April 26, 2024
Last bits of Rehoboth Beach Patrol building knocked down Friday, February 23, 2024
Rehoboth Beach Patrol demo is officially underway Monday, February 5, 2024
Demo of old Rehoboth Beach Patrol building has begun Monday, January 29, 2024
Rehoboth exploring temporary options for beach patrol in 2024 Saturday, December 23, 2023
Rehoboth completes projects, nears start of beach patrol work Friday, December 8, 2023
Rehoboth moving forward on beach patrol project Friday, November 17, 2023
Rehoboth Beach Patrol project may be delayed to 2024 Monday, November 13, 2023
The weather conditions were a little rough, but crews successfully installed steel sheet piles that will protect important underground infrastructure at the new Rehoboth Beach Patrol in the event of a major storm.
A crane moved in a little more than two weeks ago; the construction crew battled poor weather the whole time. It rained the whole first week, causing the site to flood, while the second week saw multiple days of high winds. Installation equipment included a crane with a 90-foot boom and a vibro hammer, which is the green piece of equipment sitting on top of the steel pile.
In addition to the weather, workers ran into a stubborn rock about 25 feet below the surface as they were installing the steel piles. The rock appears to be debris from the infamous March 1962 storm, said a city Facebook post.
Lynne Coan, city spokesperson, said the next step is the continued installation of stormwater infrastructure next week. When complete, crews can begin foundation work for the main building. Foundation work will include driving piles, bonding and pouring concrete, Coan said.
Construction of the new $5 million, two-story facility with public restrooms on the Boardwalk level and beach patrol headquarters on the second floor is expected to take about 18 months.
Hydraulic Vibratory Hammer This coming summer, the beach patrol will have a split operation – one location at the chamber information booth at the end of Delaware Avenue and another in the dirt parking lot at the end of Lake Avenue.